Where can I see buildings that use the GLM Emmedue building system?

Please see the projects and news pages of our web site for examples of buildings made using GLM Emmedue panels. GLM have to date supplied UK and Ireland. Worldwide there are over 1 million buildings made using the same Emmedue M2 technology (even Antartica).

Can the system be extended onto a traditional built structure?

Yes, this can easily be done by installing 40cm long anchoring bars (rebar) every 30cm in the structure of an existing building.

Once constructed, can properties be extended upwards or do sub-floors need extra structural support?

The single panel is structural to four stories and if used as internal walls then all elements are structural. For larger structures, the M2 double panel is suitable.

As there is no cavity, how are additional pipes and cables inset after the build?

In the UK we can specify plasterboard on the internal walls to allow for extensions and movement of fittings. All ceilings have a height void from 38mm- 75mm which again makes movement of fittings easier for homes that do not use the plasterboard approach. A wall chaser can also be used.

How long does it take on average to build a typical house?

While the GLM Emmedue Building shell can be erected in hours, it depends on how the house is being constructed. For a single home of 9 x 5m at height 8.3m we could make a 4 bed with two bathrooms in this footprint and provide c.120m2 of floor space over ground, on the first and second floor. Using a rendered finish, the build would be less than three months from finalisation of design to handover, allowing time for the concrete to cure (28 days).

A six-home project would be completed in five months, with a five-person team, by moving between them as the concrete cures.

For large-scale projects we can provide several hundred homes in less than five months, but we are restricted by the capacity of the building site and not the factory. Our factory has the current capacity for more than 4000 SQM of panels per day, based on a 400 SQM building, that is 10 houses per day, which can be increased as required.

Other options include precast units that could be made away from the building site, ready to be craned into position either as panels or modules.  The disadvantage here is that precast units limit your design flexibility.

What are the points of improved difference between standard structured insulated panels and M2?

The standard SIP panel is a timber panel with insulation in the middle. The wooden SIP panel itself is not waterproof and requires additional services including weatherproofing /render etc to be applied to make the system suitable for use. Also, the timber SIP panel is not fireproof without again additional rendering/brickwork etc.

Therefore, overall, the timber SIP is more costly, requires more trades, and requires a crane on-site to erect and install. The Emmedue SIP by GLM is light weight, and when concreted is weatherproof, fireproof, waterproof, and structural to 4+ stories, and no cranes are needed. In addition, the carbon footprint of the Emmedue SIP is lower than that of the timber frame SIP systems.

What are the components used in the process?

Pearls are expanded using steam to form Expanded Polystyrene Sheet’s (EPS) which are more than 90% air. The remaining % is made up of oil and fire retardant.

Are the SIP M2 panels high-risk flammables?

No, the EPS pearls are fire retardant, so they are self-extinguishing and as such stable, unless a continuous fuel source is available to feed a fire. EPS is combustible when the temperature goes over 550Øc, whereas wood combusts at 450øC. EPS is stored in many shop outlets without risk to consumers, the building, or staff. The panels are more than 90% air, with the other % oil and fire retardant.

Does the product meet all building regulation in the UK?

Yes, Local Authority Building Control have assessed our panels with regard to housing, and we have been accredited with LABC Assured status, we are one of less than 10 companies that have such status for the whole structure of the house. We continually improve our advanced building system, working with trade associations, research organisations and hold building warranties approved for the system.

Does the system require construction workers to have special skills?

The panels can be set up and assembled using just two people with minimal equipment, with no lifting equipment required. The spraying of the panel with shotcrete in the case of the Single Panel, most find is easier than applying plaster undercoat.

When using the Double Panel the application of Shotcrete is not required due to the cavity being filled with Concrete.

What specific H&S issues come with the product or building technique?

For the handling and install of the panel, to minimise the risk of grazes and cuts from the exposed metal mesh on the panels – it is advised you wear long sleeve shirts and gloves.

In high winds two people should carry a panel and ensure that they are secured and strapped to stop lifting.

Concrete should be kept away from skin by appropriate planning and where needed the use of PPE (typically boots).

How does the structure withstand impact from storms or vehicles?

The Emmedue Building System is exceptional in withstanding everything from tornadoes to bullets, explosions, and earthquakes. More videos can be shown of this.

 

Doesn’t polystyrene melt in the heat? How would these units withstand the high heat of a fire?

The EPS in the Emmedue M2 Panel does not melt as it is kept cool. In the test video you can see the temperatures applied exceeds 1000c, but the exterior temperature is measured at less than 40c. The mesh and concrete conduct energy away to the whole surface (spreads load in the same way).

What if the panels crack or the rendering falls off in full or in part, exposing the core to the source of the heat?

In that case, the EPS would eventually melt but tests have shown that this does not happen even after 150 minutes at 1000C – the standard home needs protection for 60 minutes and even in high rise and public buildings, the requirement is only 120 minutes. And as mentioned above, the M2 system does not add fuel to the fire, so if there is no continued fuel source, the fire will not spread.

Are there restrictions on external and internal cladding or coating?

There is no minimum spec as the use of the structural concrete delivers a watertight structural finish that can be painted but this is not a necessity. However, any additional outer skin can be fixed to the external building fabric, including brick slip, cladding, or any acrylic render. A single application of speciality blended concrete products are used to increases output without loss of strength or waterproofing.

Is the polystyrene (EPS) panel covered in a concrete render? If so, that’s not particularly green is it?

The design of the panel is such that concrete, and metal are reduced in weight and volume but by integrating with the EPS insulation it can be used on its own as single panels for 4 stories.

In comparison to glass, steel, gypsum board, and bricks and for structural applications, the M2 system utilises less CO2 in construction and in use; we can even outperform the carbon balance of wood systems. The concrete we use has a CO2 cost of 121gCO2/kg material. By contrast, plasterboard is nearly 2000gCO2/kg. When creating a structural external wall for a house, M2 only requires 80mm of concrete, which is the same width as a single brick, meaning the CO2 output is far less than a traditionally built house.

EPS is misunderstood as a product by many. When you know it is more than 90% air you can start to understand why its carbon footprint is much lower than you might have expected. EPS is by most measures the most green insulator, better than foamed glass, rockwool and mineral wool. Furthermore, by using the GLB system there is a significant amount of energy/carbon saved by reducing the concrete required and avoiding the need for other materials.

What is the recyclable potential if in 70 years properties were to be demolished?

With the correct equipment the building can be recycled, using a vibro impactor. Prior to this, all wiring can be removed before demolition because we use conduit for the electrics. Using a vibro impactor the concrete is separated from the EPS/Steel mesh, then the mesh can be cut and recycled. The EPS can then be washed and compressed to make new insulation.

Redefining Modern Methods of Construction

Low Carbon & Sustainable

Simple construction using UK made Polystyrene and fine concrete to provide an extremely low carbon build simply and efficiently. Our sustainable system creates less CO2 in construction (33kgCO2e/m2) and saves over 65% of user energy requirements than traditional homes and our panels provide less waste in design and production, they can be recycled and, thanks to being lightweight, it saves on transport.

Versatile

Any shape, structural or not, our panels can be cut on site to any geometric shape so give full design flexibility, offering a complete range of building elements: load-bearing walls, curtain walls, floors, ceilings, roofs, and stairs. Mix and match with other systems.

Robust

Our advanced building system has undergone internationally recognised laboratory tests that prove the structural strength of its monolithic joints, meaning it can withstand earthquakes and cyclone as well as day to day family life. Fix to the walls wherever you like.

Fire Resistant

Panels are made of self-extinguishing expanded polystyrene, completely encapsulated in reinforced concrete which cover the sides of panels and prevent combustion. They meet international fire resistance standards, providing an REI rating of 120 minutes.

Speedy

The Advanced Building System reduces construction times by as much as 50% compared to traditional building methods.

Better Value Lower Carbon

A raw structure made with GLB panels can cost up to 40% less than a traditional structure of comparable market value. Plus, panels are machine made and assembly processes are optimised, leading to big savings on labour costs and all with a carbon benefit too.

Projects

The panels produced using the EMMEDUE (M2) technology have been used to construct over 1 million buildings all over the world using offsite construction in various ways, from modules through to panels provided for the self-build market.

View All
ipad mockup

Make a difference and change the way you build today

We know you are under pressure to reduce construction costs and build time, while also building in a more sustainable way. Our building system will provide you with greater speed of construction, a lower carbon footprint and better value than traditional bricks and mortar, steel, or timber frames. So, why not change the way you build today?

Price Your Job

    Sign up to our newsletter








    By submitting your details you confirm that you agree to the storing and processing of your personal data by Green Life Buildings as described in the privacy statement.

    We’d like to keep in touch

    To find out how Green Life Buildings can help you with your latest project, fill out the contact form below.




      By submitting your details you confirm that you agree to the storing and processing of your personal data by Green Life Buildings as described in the privacy statement.


      Skip and continue